EPC of 34 MW Gas Turbine Generator Frame 6, 115 kV Substation, and all associated Equipment at Caltex Minas Power Plant No.9. Construction Period: Jun ‘93-Dec ‘94 Project Cost: US$14,750,000 Owner: PT.Caltex Pacific Indonesia (Chevron) |
|
|
EPC of 34 MW Gas Turbine Generator Frame 6, 115 kV Substation and all associated Equipment at Caltex Minas Power Plant No. 10. Construction Period : Dec ‘93-Apr ‘95 Project Cost : US$12,900,000 Owner : PT.Caltex Pacific Indonesia (Chevron) |
|
|
EPC and Maintenance of 34 MW Gas Turbine Generator Frame 6, 115 kV Substation, and all associated Equipment at PLN Pontianak. Construction Period : May ‘96-Jan ‘98 Maintenance Period : Jan ‘98-Jan ‘99 Project Cost : US$13,500,000 Owner : PT. PLN (Persero) |
|
|
EPC and O&M of 2×20 MW Gas Turbine Generator Frame 5, and all associated Equipment at Jack Up Platform Seafox 3, Widuri CNOOC SES LTD. Construction Period : Jun ‘00-Aug ‘02 Project Cost : US$30,000,000 Operation Period : Nov ‘01-Aug ‘12 Owner : PT. Kwartadaya Dirganusa Partner : Seafox BV. |
|
|
EPC and O&M of 20 MW Gas Turbine Generator GE Frame 5 and all associated Equipment at Pupuk Iskandar Muda, Lhokseumawe. Construction Period : Sep ‘02-Aug ‘03 Project Cost : US$10,000,000 Operation Period : Aug ‘03-Aug ‘13 Owner : PT. Kwartadaya Dirganusa |
|
|
Engineering and Construction Supervision of 2×34 MW Gas Turbine Generator Frame 6 and all associated Equipment at PUB Plant Changi, Singapore. Construction Period : Nov ’02-Mar ‘04 Operation period : Mar ’04-Mar ’06 Project Cost : US$1,000,000 Owner : PUB Singapore |
|
|
EPC of 20 MW Gas Turbine Generator, Rolls Royce RB 211, 150 kV Construction Period : Jan ’02-Mar ’03 Project Cost : US$12,700,000 Owner : PT Menamas Mitra Energi |
|
|
EPC of 2×25 MW Gas Turbine Generator RB 211, 150 KV Construction Period : Aug ’03-Aug ’04 Project Cost : US$30,000,000 Owner : PT Mitra Energi Batam |
|
|
EPC and O&M of 2×25 MW Gas Turbine Generator RB 211, 150 KV Construction Period : Jan ‘05-Aug ‘05 Operation period : Aug ‘05-Aug ‘15 Project Cost : US$ 31,000,000 Owner : PT Dalle Energy Batam |
|
|
EPC and O&M of 20 MW Gas Turbine Generator GE Frame 5 at PLN Teluk Lembu I, Pekanbaru. Construction Period : Sep ’04-Sep ‘05 Operation period : Sep ’05-Sep ’15 Project Cost : US$ 2,000,000 Owner : PT Riau Power |
|
|
MFO-nization Combined Cycle Power Plant 450MW at PLN Tambak Lorok, Semarang. Construction Period : Aug’08 – Apr’09 Project Cost : US$ 20,000,000 Partner : Thommasen Intl./Modaco Enersys Owner : PT. Indonesia Power |
|
|
EPC of 20-25MW Gas Engine Power Plant Bergen Rolls Royce and all associated Equipment at PT Pelayanan Listrik Nasional Batam – Panaran Construction Period : Sept.’11–Nov.’12 Project Cost : US$20,000,000 Owner : PT. PLN Batam Contractor : Consortium Medco-Dalle-TDIL |
|
|
EPC of 2x35MW Gas Turbine Power Plant Frame 6 and all associated Equipment at PT. Energi Listrik Batam – Tanjung Uncang, Batam Construction Period : Sept.’12–Dec. ‘14 Project Cost : US$28,000,000 Owner : PT. Energi Listrik Batam Partner : Medco Power Indonesia |
|
|
EPC and Maintenance of Fajar Surya Wisesa Cogeneration Plant, Consists of 34 MW Gas Turbine Generator Frame 6, Construction Period : Sep ’94-Sep ’95 Maintenance Period : Spe ‘95-Sep ‘96 Project Cost : US$16,000,000 Owner : PT. Fajar Surya Wisesa |
|
|
EPC for Repowering Electrical Project 75MW at PT. Indocement Tunggal Prakarsa, Tbk. Citeureup, Bogor. Construction Period : Apr ’15 – Feb’16 Project Cost : US$ 14,000,000 Patner : Siemens Owner : PT Indocement |
![]() |
Construction of Geothermal Power Plant Ansaldo 55MW and all associated Equipment at Dieng California Energy. Construction Period : Apr ’96-Dec ’97 Project Cost : US$ 10,000,000 Owner : California Energy (Geodipa) Partner : Kiewit Holt Intl. |
|
|
Construction of Darajat Geothermal Power Plant Mitsubishi 70 MW and all associated Equipment at Amoseas Darajat. Construction Period : Aug ‘97-Aug ’98 Project Cost : US$ 6,000,000 Owner : Amoseas (Chevron) Partner : Hyundai/ Stone & Webster |
|
|
EPC of 2×300 MW Coal Steam Power Plant and all associated Equipment at PLN Sudimoro, Pacitan, Jatim. Construction Period : Aug’07 – Aug’12 Project Cost : US$576,000,000 O&M : PT. PLN PJB Partner : Dongfang Electric Corp. Owner : PT. PLN (Persero) |
|
|
EPC of 3×300 MW Coal Steam Power Plant and all associated Equipment at PLN Lontar, Teluk Naga, Banten. Construction Period : Aug’07 – Aug’12 Project Cost : US$820,000,000 O&M : PT. Indonesia Power Partner : Dongfang Electric Corp. Owner : PT. PLN (Persero) |
|
|
EPC of Central Gathering Station No.10 at Caltex Duri. Construction Period : Apr ’99-Apr ’01 Project Cost : US$45,000,000 Owner :PT.Caltex Pacific Indonesia (Chevron) |
|
|
EPC of LPG PLANT and GAS COMPRESSION 6.2 MMSCFD at ARCO Pagerungan Besar Island. Construction Period : Oct ’95-Dec ’97 Project Cost : US$6,000,000 Owner : ARCO |
|
|
Construction of Desulfurization Plant at Santa Fe Tuban. Construction Period : Oct ’98-Jul ’99 Project Cost : US$1,000,000 Owner : Santa Fe |
|
|
Construction of Automatic Well Testing and Degassing Station at Caltex Duri Construction Period : Feb ’00-Apr ‘01 Project Cost : US$3,000,000 Owner : PT. Caltex Pacific Indonesia (Chevron) |
|
|
EPC for New Gantry System (NGS) an End to End Data Automation (ETEDA) at Terminal BBM Rewulu – Yogyakarta Construction Period : Nov ’14-Oct ’15 Project Cost : US$6,000,000 Owner : Pertamina Patra Niaga, Dwi Sura Prima (DSP) |
|
|
EPC for New Gantry System (NGS) at Terminal BBM Pengapon – Semarang Construction Periode : Jul ’15-Jun ’16 Project Cost : US$5,000,000 Owner : Pertamina Patra Niaga, Dwi Sura Prima (DSP) |
|
|
EPC of 115 kV 8 Delta Substation at CALTEX MINAS Construction Period : Jun ’97-Feb ’98 Project Cost : US$1,800,000 Owner : PT. Caltex Pacific Indonesia (Chevron) |
|
|
Construction of South Gas Pipe Line 7Km, 24 Including Civil Work at Caltex Duri Construction Period : Mar.’00-Jul.’00 Project Cost : US$600,000 Owner : PT. Caltex Pacific Indonesia (Chevron) |